Capacity & Feasibility System

Find out what your team can actually deliver before you commit to it.

Capacity & Feasibility System

What this fixes

Teams commit to work before they know what it really costs them. The commitment is concrete - a named project, a promised date. The capacity it will eat is vague. So the team says yes, again and again, and only finds out it is over capacity once the work is late and people are stretched. This makes the hidden cost of each commitment visible up front, so the team can see what it can actually afford before saying yes.

How this works

An engineering team commits to six roadmap items for the quarter. Everyone agrees they’re important, and the plan looks achievable. Two weeks later, production incidents eat into the team’s time; two engineers are pulled into customer escalations, and one feature turns out to be twice as complex as expected. By the end of the month, the team is already overloaded. The problem wasn’t that it worked too slowly - it committed before it knew what the work would really cost.

So picture your team’s real capacity as a fixed pool of tokens. That pool is all you have - and some of it is already used up by work in flight. Now picture the commitments you’ve taken on, each with its real cost turned face down.

The team spends its capacity tokens on those commitments - guessing the cost. Then the real costs are turned over. Almost always, they add up to more capacity than the team has: you’re already over before adding anything new. So you take commitments off the table until you’re back within what you actually have. The ones you remove are the ones you wanted but can’t afford - and that is the moment the lesson lands: we said yes before we knew the cost.

Team: one person acts as the facilitator - they run the activity using the Facilitator Guide while everyone else takes part.

Time required

Team ✓

Team: 45–90 minutes, with a facilitator. Best run at a planning or commitment point, with the people who own the work.

The time required is indicative and will depend on the nature of the problem and the size of the team.

The facilitator should read the short facilitation guide first - about 8–10 minutes. It is a downloadable PDF on this page.

When to use

Bring the real set of commitments you’re about to take on - a quarter, a release, a roadmap - before you’ve said yes, not after.

Use it whenever:

  • you’re about to take on a batch of work and want to know what you can really afford
  • every planning round ends with more commitments than the team can deliver
  • the true cost of each piece of work is unclear until you’re deep into it
  • the team keeps starting already over capacity, then scrambling
  • you need a clear, defensible limit to hold against the next request

What you get

  • A clear picture of your real capacity - and how much is already spoken for
  • The true cost of each commitment, out in the open
  • The commitments you can actually deliver - and the ones you deliberately chose not to take on

You’ve done it well when: the team can see it was already over capacity, can point to what it dropped and why, and leaves with a set of commitments it can deliver.

What you’ll notice

  • The real cost was bigger than anyone guessed
  • You were already over capacity before adding anything new
  • Saying no gets easier when you can see the tokens run out

Why this works

Teams don’t overcommit because they’re greedy - they overcommit because the commitment is concrete and visible while its cost stays hidden. You can’t say no to a real list with an imaginary limit. Once every commitment has a real cost and your capacity is a fixed pool you watch run out, the gap stops being a guess and becomes real - and saying yes and saying no become realistic decisions.

What you need

Everything comes in one kit. Here is each piece, what it is, and when you use it:

Capacity tokens (one pool for the team).  Small tokens that stand for your team’s real capacity - for example, one token = half a person-week. You count out the team’s true capacity in tokens at the start. This is all the team has to spend.

“Already in flight” markers.  A few tokens in a different colour for the work the team is already doing. You set these aside first - they are spent before any new commitment, so the team sees how little is really free.

Commitment cards (with a hidden cost).  One card per piece of work the team is taking on. Each card has its real capacity cost printed on the back or under a flap, so it stays hidden until the reveal. The team writes its own commitments on blank cards; the facilitator sets the hidden cost.

The board.  A simple surface with two areas: a capacity area where the token pool sits, and a commitments area where the cards are laid out. You place cards and move tokens between the two as you go.

Capture space.  Room to write down the final set of commitments the team can afford, and the ones it dropped.

Roles - Team:  a facilitator (counts out the capacity tokens, sets the hidden costs, runs the spend and the reveal, keeps time) and participants (write the commitments, spend the tokens, decide what to drop).

Steps

  1. Set up (5 min). Team: appoint a facilitator first - they run the activity from the Facilitator Guide. Put the board out, with the capacity area and the commitments area marked.
  2. Count your real capacity (10 min). As a team, count out your true capacity in tokens. Count the capacity you’ll actually have - not the capacity you hope you’ll have. Put the tokens in the capacity area. This is all you have.
  3. Set aside work in flight (5 min). Take out tokens for the work you’re already doing, using the different-colour markers. What’s left is your free capacity. Notice how much smaller it is.
  4. Lay out your commitments (10 min). Write each piece of work you’re taking on, one per card. Place them in the commitments area. The real cost of each card stays hidden for now.
  5. Spend your tokens - guess the cost (10–15 min). Go through the commitments. For each one you want to keep, move the tokens you think it will cost onto that card. Once you’ve placed tokens on a commitment, don’t move them until every commitment has been estimated - otherwise the reveal loses its force.
  6. Turn over the real costs (5 min). Reveal the hidden cost on each commitment card. Compare it to the tokens you placed. Add up the true costs.
  7. See where you stand (5 min). Almost always, the true costs add up to more than your capacity. You are already over. Don’t fix it yet - just see it.
  8. Drop until you fit (10–20 min). Take commitments off the board until the true costs fit within your real capacity. Ask: which commitment gives us the least value for the capacity it consumes? Decide each on purpose: drop it, push it later, or add real capacity for it.
  9. Commit (5 min). Lock the set you can afford. Photograph the board. Keep your capacity count - it’s the limit you hold against the next request.

Output / Takeaways

  • A photo of your real capacity and the commitments that fit within it
  • The commitments you dropped, and why
  • The reusable habit: “what will this really cost us, and can we afford it - before we say yes?”

Important rules

  • Count real capacity, not the best case
  • Set aside work in flight before anything new
  • Keep each commitment’s cost hidden until the reveal - the surprise is the point
  • Don’t reduce the hidden costs after revealing them - change the commitments instead
  • You can only spend the tokens you have - no borrowing
  • This finds what you can afford before you commit - it is not a way to rank or pick favourites